AMATIS CONTROLS - PROJECT DEPLOYMENT GUIDE#
Project Deployment for Amatis Controls and X-PoE Systems#
Setting up a project with Amatis Controls and X-PoE switches requires careful coordination across design, configuration, installation, and optimization. To support successful deployments, the Project Deployment Guide offers a structured, step-by-step framework that teams should follow at the outset of any new project.
This guide should be considered a foundational reference for any Amatis or X-PoE deployment. Following it ensures reliable performance, minimal rework, and consistent results across projects.
Purpose of the Guide#
The Project Deployment Guide outlines the major activities required to bring a system from concept to commissioning. It serves as a checklist and planning tool to help:
- Ensure complete documentation and load profiling before deployment
- Align programming behavior with user expectations
- Minimize onsite troubleshooting through pre-configuration
- Streamline installation and testing
- Deliver a validated and optimized lighting control system
Deployment Workflow Overview#
The deployment process is grouped into four major phases. Each one contains best practices and task-level guidance to ensure a smooth handoff between stages:
Design & Planning:#
This initial phase focuses on gathering documentation and translating project requirements into a fully specified lighting control design.
Key tasks:
- Collect floor plans, fixture schedules, and circuiting details
- Calculate fixture loads per X-PoE port
- Assign switch/port IDs, load numbers, and device names
- Design the network architecture and power distribution
- Perform fixture testing and load profiling to establish control parameters
Pro tip
Assign unique identifiers (like XS1-3 for switches and MS-103-1 for motion sensors) early and consistently—these will be used throughout deployment.
Pre-Programming & Configuration:#
Before any hardware is installed, the system can be structured in the Amatis platform. Pre-configuration helps reduce setup time and errors later in the process.
Key tasks:
- Define light levels, switch behavior, scheduling, and occupancy rules
- Build location structure and placeholder devices in the config app
- Pre-load load types for each X-PoE port
- Assign network profiles to wireless placeholders
- Schedule a programming review for team alignment
Pro tip
Pre-programming is optional but strongly recommended. It creates a solid foundation for faster commissioning.
Installation & Deployment#
This phase brings the system to life—hardware is installed, firmware is updated, and devices are connected and configured.
Key tasks:
- Install and configure AMBRs and X-PoE switches
- Coordinate network/firewall access with IT
- Install wireless devices and update firmware
- Capture MAC addresses for all devices
- Associate live devices with placeholders using MAC tables
- Finalize wireless network migration and device communication
Pro tip
MAC address capture is critical—label and log everything during installation to simplify mapping and troubleshooting later.
Testing & Optimization#
Once installed, the system is verified and refined for performance and client satisfaction.
Key tasks:
- Sync final programming to all devices
- Validate device communication and firmware
- Test lighting scenes in various locations
- Fine-tune dimming, timeouts, and schedules
- Conduct a client walkthrough and apply any requested adjustments
Pro tip
Testing in real use conditions is essential. Simulate day-to-day behavior (e.g., occupancy, scene changes) to catch edge cases early.
Download the Guide#
Download the Project Deployment Guide (PDF)
This document includes detailed checklists, naming conventions, and best practices across all stages. It should be used as a reference from the start of any Amatis Controls or X-PoE deployment.